1 - 15 of 154 documents 1 /  11 
Date FiledSummaryPages
02/23/2017Blue Creek Wind Farm Decommissioning report 2017. electronically filed by Mr. Peter F Landoni on behalf of Avangrid Renewables.18
02/21/2017Blue Creek Decommissioning report (updated filing). electronically filed by Mr. Peter F Landoni on behalf of Avangrid Renewables and Landoni, Peter F Mr.2
02/16/2017Blue Creek Wind Farm Decommissioning Report electronically filed by Mr. Peter F Landoni on behalf of Avangrid Renewables and Mr. Peter F Landoni.16
05/12/2016Notice of Withdraw and Substitution of Counsel of Ohio Hospital Association electronically filed by Teresa Orahood on behalf of Matthew W. Warnock.3
05/03/2016Notice of Change of Address for counsel for the Ohio Power Siting Board, effective May 9, 2016. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board.3
02/04/2013Case Action Form Reopening Cases electronically filed by Mr. Jeffrey R Jones on behalf of Public Utilities Commission of Ohio.2
02/04/2013Memo closing case with an effective date of 2/4/13 electronically filed by Mr. Jeffrey R. Jones on behalf of Public Utilities Commission of Ohio.2
10/01/2012Correspondence of Van Wert County Engineer stating opinion on the final condition of the roadways used by Iberdrola and their contractors during the construction of the Blue Creek Wind Farm, filed by K. J. Wendel, PE, PS - Van Wert County Engineer.1
10/01/2012Case status form reopening case.1
09/25/2012Case Action Form to Close cases effective 09/25/2012 filed by J. Jones.1
08/31/2012Spreadsheet documenting a sound spot check conducted on March 19, 2012. The Facility was in compliance with their Certificate electronically filed by Mr. Nicholas E. Doss on behalf of The Ohio Power Siting Board.5
08/31/2012Additional information on Blue Creek Wind Farm filed by PUCO Staff.2
06/27/2012Letter stating that the Ohio Power Siting Board requires Iberdrola to repair Hoaglin Township roads to preconstruction condition as required by stipulation 41 and ORC filed by Hoaglin Township Trustees. 4
06/26/2012Notice that the Blue Creek Wind Farm achieved Commercial Operation on June 14, 2012 filed by P. Landoni.1
04/19/2012OPSB Response letter sent to Kyle J. Wendel filed by Chairman Snitchler. 1
 
1 /  11 
      
      
Attorney General:
Jones, John
Wright, William
Attorney Examiner:
Agranoff, Jay