DIS - Case Record for 09-0143-RR-RCP Skip to main content

Case Record For:

09-0143-RR-RCP

File a Public Comment
Case Title: OHIO DEPARTMENT OF TRANSPORTATION DISTRICT 11 (BEL-148-25.14 PID80131 BRIDGE DECK REPLACEMENT & NS RAILROAD CROSSING AARDOT #503355S
Status: CL-CLOSED
Industry Code: RR-RAILROAD
Purpose Code: RCP-Railroad Crossing Protection
Date Opened: 2/25/2009
Date Closed: 9/9/2010
Printable Docket Card Service List
View All
1 - 15 of 25 documents 1 /  2 
Date FiledSummaryPages
09/09/2010Case Action Form closing case effective 09/09/10.1
07/12/2010Letter stating anticipated date for project completion filed by S. Warner on behalf of the Ohio Department Of Transportation. 1
06/30/2010Service Notice2
06/30/2010Entry ordering that ODOT's request for extension of time until August 31, 2010, be granted.2
06/14/2010Letter requesting a 60 day extension, until August 31, 2010 for project completion filed by S. Warner, ODOT, District 11. 1
06/14/2010Letter stating construction should be completed July 15, 2010 filed by S. Warner on behalf of ODOT, District 11. 1
06/14/2010Staff recommendation filed by G. Martin.2
06/11/2010Request for 60 day extension for the completion of project, the gate arms have been removed for construction purposes and delays due to weather, project was to be completed July 15, 2010, extension request would allow until August 31, 2010 filed on behalf of Ohio Department of Transportation by S. Warner.1
03/03/2010Service Notice2
03/03/2010Entry ordering that the temporary downgrade for this project begin on March 15, 2010, and end on June 30, 2010, in accordance with this entry and that ODOT and NS comply with finding (4).2
02/18/2010Memorandum of Staff recommending that the Commission grant the temporary downgrade through June 30, 2010 filed by G. Martin.2
02/10/2010Letter stating that construction for BEL-148-25.12, PID 80131 is scheduled to begin on March 15, 2010 filed by S. Warner on behalf of Ohio Department of Transportation.1
07/01/2009Service Notice2
07/01/2009Entry approving temporary downgrade to be held in abeyance and that ODOT and NS comply with finding (4).3
06/24/2009Service Notice2
 
1 /  2 
      
      
Attorney General:
Attorney Examiner:
Farkas, Scott