Date Filed | Summary | Pages |
06/02/2009 | Letter notifying the Commission that this construction project was completed on approximately May 22, 2009, filed by J. Toth on behalf of FirstEnergy Service Company. | 1 |
01/16/2009 | Letter stating that construction of ChrysIer-O.I. Levis 138 kV Transmission Line Tap Extension for the Lime City Distribution Substation project will begin on January 12, 2009 filed by J. Toth on behalf of FirstEnergy Service Company. | 1 |
07/11/2008 | Staff Investigation Report and Recommendation for the Lime City Distribution Substation. | 1 |
06/17/2008 | In the matter of the letter of notification of the American Transmission Systems, Incorporated for the Chrysler-O.I. Levis Park 138Kv Transmission Line Tap Extension for The Lime City distribution substation project. | 23 |