Case Record For  07-0715-EL-BTX

Case Title: AEP-OHIO
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 6/19/2007
Date Closed:
Printable Docket Card Service List
View All
1 - 15 of 47 documents 1 /  4 
Date FiledSummaryPages
12/23/2009Letter of Notification electronically filed by Mr. Matthew J Satterwhite on behalf of Ohio Power Company.2
08/14/2009Service Notice1
08/14/2009Entry granting CSP's motion for an extension of the protective order. (GS)2
06/19/2009Motion for protective order and memorandum in support filed by S. Nourse on behalf of American Electric Power Service Corporation.3
06/18/2009Motion for protective order and memorandum in support for extension filed on behalf of Columbus Southern Power Company by S. Nourse. (FAX)3
02/10/2009Response letter to Mr. Tommy Antill, Project Manager on behalf of the Ohio Power Siting Board filed by K. Lambeck. 1
01/26/2009Response letter to: Tommy Antill, Project Manager, on behalf of the Ohio Power Siting Board filed by K. Lambeck. 1
01/16/2009Response letter to: Tommy Antill filed on behalf of OPSB Staff, K. Lambeck.1
12/12/2008Letter to AEP regarding the commencement of construction on the Don Marquis 138kV Loop #1 Project filed by K. Lambeck, OPSB.1
11/04/2008Response letter sent to Mr. Antill filed by K. Lambeck.1
10/28/2008Notice stating that construction on the Don Marquis 138kV Loop #1 Project will be commenced on or about November 4, 2008, filed by S. Nourse on behalf of Columbus Southern Power Company dba American Electric Power.1
09/26/2008Notice to Ohio Power Siting Board that tree clearing on the Don Marquis 138 kV Loop Project will commence on or about October 13, 2008 filed by S. Nourse on behalf of American Electric Power Service.1
06/02/2008Service Notice1
06/02/2008Entry ordered that the Stipulation filed by the parties is approved and adopted; that a certificate be issued to CSP for the construction, operation, maintenance of the project as proposed along the preferred route; that the certificate contain the 29 conditions set forth in Section V. of this Opinion, Order, and Certificate. (OPSB)30
05/16/2008Letter regarding the habitat survey for the Indiana bat and the timber rattlesnake and impacts related to the Don Marquis 138kV Loop #1 Project filed by S.Nourse on behalf of AEP Service Corporation.4
 
      
Attorney General:
McNamee, Thomas
Parrot, Sarah
Attorney Examiner:
See, Greta
Staff Contact:
 
 
The Public Utilities Commission of Ohio
180 E. Broad St., Columbus, OH 43215
Ted Strickland, Governor • Alan R. Schriber, Chairman
An Equal Opportunity Employer and Service Provider
(800) 686-PUCO (7826) - (800) 686-1570 (TTY-TDD)