Date Filed | Summary | Pages |
09/15/2006 | Memo stating that the grade crossing improvements/upgrades ordered and or agreed been completed and installed filed by PUCO staff G. Martin. | 1 |
09/14/2005 | Service Notice | 2 |
09/14/2005 | Entry ordering that CUOH submit to the Commission and ORDC site plans and cost estimates for the projects within 90 days of the date of this entry, following approval of site plans and cost estimates, proceed with construction to be completed by September 14, 2006, upon completion of the project, at which time staff will make its final inspection and file a memorandum in this docket directing docketing division to close case. | 3 |
08/08/2005 | In the matter of the authorization of the Columbus & Ohio River Railroad to modernize an active warning device in Harrison County, Village of Scio, SR 646/Main St., DOT # 510-726S. | 6 |
|