Date Filed | Summary | Pages |
02/24/2005 | Memo stating the warning device improvements/upgrades ordered have been completed and placed in service; that this record be closed filed by PUCO staff. | 1 |
02/17/2005 | Service Notice | 1 |
02/16/2005 | Entry ordered that an extension of the construction deadline until March 17, 2005, be granted (SF) | 2 |
02/15/2005 | Memo filed on behalf of PUCO staff recommending 30 day extension requested by Indiana & Ohio Central Railroad. | 2 |
02/15/2005 | Letter requesting a 30 day extension to allow for Installation of electric service at location, filed on behalf of Indiana & Ohio Railroad by A. Satunas.(FAX) | 1 |
02/19/2004 | Entry ordering that I&O submit to the Commission and ORDC site plans and cost estimates for the project by May 19, 2004, that by May 26, 2004, I&O file a letter in this docket advising that is has submitted site plans and cost estimates to the Commission and ORDC, that following approval of site plans and cost estimates by ORDC and I&O proceed with construction of the project, with construction to be completed by February 19, 2005, that I&O notify the Commission and ORDC 30 days before the projected date of completion, at the time staff or ORDC makes its final inspection and if it finds that the installation is completed and has been put in service, staff will file a memorandum in this docket directing the docketing division to close this case. | 3 |
02/19/2004 | Service Notice | 1 |
02/05/2004 | In the matter of the authorization of the Indiana & Ohio Central Railway to install an active grade crossing warning device in Fairfield County. | 3 |
|