Case Record For  00-1527-EL-BGN

Case Title: FREMONT ENERGY CENTER/SANDUSKY OH
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BGN-Application for a certificate/ generating station
Date Opened: 8/21/2000
Date Closed: 5/21/2001
Printable Docket Card Service List
View All
1 - 15 of 72 documents 1 /  5 
Date FiledSummaryPages
03/04/2008Service Notice4
03/03/2008Entry ordering that the application to transfer the certificate of environmental compatibility and public need for the construction and operation of the 704-MW electric generating station in Fremont, Sandusky County, Ohio from Calpine to FirstEnergy Generation Corp. is granted upon terms set forth in finding (5). (OPSB)3
02/15/2008Amended joint application to transfer a certificate to FirstEnergy Generation Corp. filed on behalf of Calpine Corporation, Inc and FirstEnergy Generation Corp. by S. Bloomfield and C. Schraff. 2
02/11/2008Joint application of Fremont Energy Center LLC and FirstEnergy Generation Corp.to transfer certificate filed on behalf of FirstEnergy Generation Corp. by S. Bloomfield and C. Schraff. 3
12/22/2006Report on construction activity for year 2006, filed on behalf of Fremont Energy Center by K. Florence.1
06/02/2005Annual progress report of Fremont Energy Center Construction filed by J. Garvey.2
01/13/2005Service Notice2
01/10/2005Entry approving the joint application of Calpine and ATSI permitting ATSI to assume the obligations of the certificate conditions related ti the Fremont Energy Center switchyard.3
11/16/2004Staff investigation report and results filed by staff.1
11/15/2004Joint application for approval of assumption of certificate conditions that apply to the switchyard associated with the Fremont Energy Center filed by S. Bloomfield on behalf of Calpine Corporation and C. Schraff on behalf American Transmission Systems Incorporated.3
02/26/2004Staff has reviewed the FirstEnergys drawing T-675-04-01 titled West Fremont Property Plan for the Ohio Power Siting Boards review and approval.1
02/18/2004Drawing T-675-04-01, titled "West Fremont Property Plan" for the OPSB's review and approval, filed on behalf of FirstEnergy Service Corp. by T. Krauss.3
12/15/2003Entry ordering that the May 21, 2001, as amended on June 18, 2001 certificate of environmental compatibility and public need previously granted to Fremont Energy Center, LLC for the construction and operation of a 704-MW electric generating station in Sandusky Township, Sandusky, Ohio, shall be transferred to Calpine Corporation, ordered that Calpine Corp. shall be bound by and comply with all terms and conditions of the certificate.(OPSB)3
12/15/2003Entry ordering that the May 21, 2001, as amended on June 18, 2001 certificate of environmental compatibility and public need previously granted to Fremont Energy Center LLC for construction and operation of a 704-MW electric generating station shall be transferred to Calpine Corporation and that as a result of transfer, Calpine Corporation shall be bound by and comply with all terms and conditions of this certificate.3
11/24/2003Letter confirming merger closed on November 18, 2003, filed on behalf of Fremont Energy Center, LLC by S. Bloomfield.1
 
      
Attorney General:
Wright, William
Attorney Examiner:
Farkas, Scott
Staff Contact:
 
 
The Public Utilities Commission of Ohio
180 E. Broad St., Columbus, OH 43215
Ted Strickland, Governor • Alan R. Schriber, Chairman
An Equal Opportunity Employer and Service Provider
(800) 686-PUCO (7826) - (800) 686-1570 (TTY-TDD)