Date Filed | Summary | Pages |
01/30/2001 | Letter stating that applicant completed construction on the Chamberlin-Valley 138 kV Loop to Theiss Road Substation project on January 22, 2001, filed on behalf of applicant by T. Krauss. | 1 |
09/05/2000 | ICN #0005 Proof of Publication filed. (2 pgs.) | 2 |
07/27/2000 | Investigation report approving the Construction Notice, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
07/27/2000 | Response to Construction Notice, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
07/27/2000 | ICN #0004 Investigation report approving the construction notice, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
07/27/2000 | ICN #0003 Response letter to Mr. Thomas C. Burgess, First- Energy Corp., filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
07/12/2000 | Letter of Notification. Filed by: T. Burgess. | 18 |
07/12/2000 | Letter of Notification. Filed by: T. Burgess. (18 pgs.) | 18 |
07/11/2000 | ICN #0001 In the matter of the Letter of Notification and motion to waive the ninety day filing requirement of Ohio Edison Company involving the construction of a 0.03 mile double circuit, 138 kV transmission line loop from the Chamberlin-Valley (CF) 138 kV transmission line into the proposed city of Cuyahoga Falls' Theiss Road 139-69-12.47 kV substation. (22 pgs.) | 22 |
07/11/2000 | ICN #0001 In the matter of the Letter of Notification and motion to waive the ninety day filing requirement of Ohio Edison Company involving the construction of a 0.03 mile double circuit, 138 kV transmission line loop from the Chamberlin-Valley (CF) 138 kV transmission line into the proposed city of Cuyahoga Falls' Theiss Road 139-69-12.47 kV substation. | 22 |